Power Distribution System Modernization & Strengthening Project Phase II in Kenya
The contract value of phase-II Kenya urban electric network transformation project is RMB 636.6 million, which is situated in eastern coastal Kenya. It includes the erection of 220KV 212.6-km single circuit line and 132KV 108-km single circuit line and the construction of three new 220/33KV transformer substations, and the scope of work includes the design, civil engineering, providing equipment and materials, installation and commissioning. The total duration of the engineering construction is 36 months.